In June, Duncan Fuller of EB5 United took a group of EB‑5 investors on an on-the-ground tour of our Priority Processing Rural EB‑5 Project, Cormont at Deer Valley East Village, meeting the people building it and getting answers to the questions investors actually ask. The visit comes just three weeks after the previous construction update, with Building 5 now topped off and the rest of the site progressing daily.
Sheila Hall (Director of Real Estate Sales, Deer Valley East Village) opened with what set Cormont apart within the broader East Village master plan.
Matt McKinnon (Senior Construction Manager, Reef Capital Partners) covered where construction actually stood and why Jacobsen Construction was brought on as a self-performing contractor on the critical path.
Jon Day (CFO, Reef Capital Partners) walked through how the Project was capitalized and how Towers 1, 2, and 5 can also be utilized to retire that debt at turnover, with no cost passed on to buyers. He also touched on what’s lined up if any piece of the financing, including the EB‑5 raise, comes in lighter than expected. As well, he explained REEF’s own balance sheet standing behind it.
- Cormont Deer Valley Construction Updates With Investors
- Deer Valley East Real Estate Market with Sheila Hall
- Why is Cormont selling so well vs all the other products in Deer Valley East?
- Cormont construction details from Construction Manager Matt McKinnon
- Cormont Construction Update with Sheila Hall
Cormont Deer Valley Construction Updates With Investors
In this video, Duncan leads EB5 United’s first large investor tour of Cormont, joined by teams from Reef Capital Partners and Jacobsen Construction. The visit comes just three weeks after the previous construction update, with Building 5 now topped off and the rest of the site progressing daily.
Key Takeaways
- The Deer Valley East Village master plan represents an estimated nearly $5.5 billion of development, with Cormont at the center, alongside Tower 1 and the neighboring Four Seasons
- Extel will retain ownership of the ground-floor retail space, requiring restaurants and shops to stay open 350 to 360 days a year to drive the year-round destination
- The first units are expected to finish this year
- The reservoir offers wakeboarding, wakesurfing, boating, and power boating, plus hiking access, making Deer Valley East a true 365-day-a-year, ski-in ski-out resort
Deer Valley East Real Estate Market with Sheila Hall
In her talk, Sheila explained why buyer confidence in the village remained strong, pointing to both Cormont’s standing within the Project and Deer Valley East’s growth as a location.
About Cormont
She explained that Cormont had drawn growing interest within the village, with buyers eager to understand the Project alongside larger brand names like Four Seasons and Waldorf Astoria. On sales, Towers 1 and 5 were roughly 85% sold, Tower 2 had just launched its first sales, and Tower 4 was set to launch by year-end at a higher price, with Tower 3 following about a year later, projected to average $3,000 per square foot against today’s comparable pricing of $3,500 per square foot.
About Deer Valley
She also talked about Deer Valley East Village itself: a development backed by more than $500 million in local government bonds, anchored by Four Seasons, Waldorf Astoria, and Cormont, and owned by Altera (KSL Partners and the Crown family), with a major village opening expected in 2028. Hall pointed to that ownership and the brands’ own vetting of the Project, along with Four Seasons’ record $4,700 per square foot sale, as the reasons behind that confidence.
Why Is Cormont Selling So Well Compared to All the Other Products in Deer Valley East?
Sheila also explained the reason behind Cormont’s sales momentum. Cormont was 25% sold, with nearly 100 units having moved in the year and a half since serious pre-sales began, a pace that had outpaced expectations. When asked why, Hall pointed to several factors:
- The simultaneous launch of Four Seasons, which drove significant traffic to Cormont
- A built-in waitlist of roughly 1,100 buyers, built over her five years selling in the village, which converted directly into early Cormont demand
- Reef’s reputation and its network of repeat investors and buyers, a meaningful driver of trust and referral sales
- A national broker network, paid the same commission as local Utah agents (an uncommon practice), key to reaching Cormont’s largely out-of-state buyer base
Cormont Construction Details from Construction Manager Matt McKinnon
Reef Capital Partners CFO Jon Day spoke with Cormont’s Construction Manager Matt McKinnon about the Project’s construction progress, its partnership with general contractor Jacobsen, and the workforce advantages of building near Salt Lake City. McKinnon had managed the Project since its early planning and design phase three years earlier, and reported the team was on schedule and, in some respects, ahead of it.
Construction Progress
- Concrete work began in late summer 2025
- Tower 1 was roughly 14 days from topping out
- MEP work was underway on the below-grade levels (P0–P2)
- Team was targeting substantial completion next year
About Jacobsen
- McKinnon described GC Jacobsen as a partner that shares Reef’s goals, which he credited for keeping the Project on track
- They self-performed the concrete work and subcontracted interior finishes, glazing, and mechanical/plumbing
- Their winter-construction methods had kept crews pouring through Utah winters and snowstorms
Cormont’s Workforce Advantage
- Most of the workforce was drawn from Salt Lake Valley and Utah County, a labor advantage few ski-destination projects have
- Recent completion of Salt Lake City International Airport’s expansion freed up both concrete supply and experienced workforce
Cormont Construction Update with Sheila Hall
Sheila Hall and Scott of Reef Capital Partners gave a July 2026 construction update on Cormont at Deer Valley. Filmed from Level 8, the top floor of Tower 1, the update took in views of Tower 5 construction, the plaza, the ice ribbon, and the skier services building, as Tower 1 neared its roof top‑off.
Key Takeaways
- Tower 1 was topping off on July 13th, with the roof and concrete deck going on
- Lower levels, including the lobby, were in rough framing, with MEP being roughed in
- Level 2 was at the same framing stage
- Formwork for Tower 1’s roof system was being placed on Level 8, confirming the July 13th top‑off date
About Cormont.
Cormont is located in Deer Valley East Village, Park City, Utah.
Cormont is an EB5 United I‑956F approved Priority Processing Rural EB‑5 Project, currently under construction within Deer Valley East Village, a master-planned community in Park City, Utah, less than one hour from Salt Lake City International Airport.
Cormont is developed by Reef Capital Partners, with a 20+ year track record in hospitality and residential development, and the EB‑5 loan is structured in 1st position on the Project’s capital stack.
Dates every EB‑5 investor should know about.
Cormont investors are filing under the current EB‑5 Reform and Integrity Act framework. For investors evaluating EB‑5 now, the Regional Center program operates against a fixed statutory clock set by Congress.
File the I‑526E petition by this date to lock in eligibility under the EB‑5 Reform and Integrity Act of 2022.
EB‑5 minimum investment amounts are scheduled to increase.
The Regional Center program will sunset unless Congress reauthorizes it by this date.
A proven platform. Verified EB‑5 Projects. Unmatched results.
Cormont’s construction and sales momentum extend a track record built on disciplined sponsor selection and structural safeguards designed to protect investor capital. Our position is built on data, not marketing.
EB5 United’s full track record, by the numbers.
More Rural EB‑5 Projects, same safeguards.
EB5 United offers additional Rural EB‑5 Projects built on the same 1st Position, senior-lending safeguards. Contact us today to learn more about currently available opportunities on EB5 United’s vetted Rural EB‑5 Project Platform.
Source. The progress details, quotations, and figures in this article are drawn from EB5 United’s June 2026 investor site visit to the Cormont Project in Deer Valley East Village, Utah, including discussion with the Reef Capital Partners development, sales, and finance teams. Construction and sales status reflect conditions on the date of the visit and are subject to change as the Project advances.
Disclaimer. This blog is for informational purposes only and does not constitute an offer to sell, a solicitation of an offer to buy, or a recommendation of any security or investment product. Information herein is based on current laws and USCIS policies as of the date of publication and is subject to change. Past approval performance is not a predictor of future processing times, and individual processing timelines may vary and are subject to USCIS adjudication. Immigration benefits are not guaranteed. This content does not constitute legal, tax, financial, or immigration advice. Prospective investors should consult their own qualified legal, tax, and immigration advisors before making any decisions.
Plan your family's future in the U.S.
Talk to our team about how the EB-5 Program works, what it costs, and how it compares to other employment-based pathways.